Start this chapter during the design phase.&#x20;

Development is structured in sprints. The IMC has small ongoing tasks during the entire development phase. &#x20;

Any adjustments or changes from the client after the design has been signed off will **not** be carried out during development, but instead **must&#x20;**&#x62;e added to the wishlist and will be addressed after website launch.

## Before the first sprint

A short meeting with the lead developer on the project with intend on agreeing on the timeline

## Sprint 1

First QA on the modules and assure everything can be set up.&#x20;

Checking if module functions works as intended and from a customer point of view

Trying to catch any bugs before the modules are handed over to the customer

## Sprint 2, 3 and forward

1. Are we on track?
2. Talk with the developers: Anything that needs fixing from previous sprint?
3. Can the products from previous sprint be delivered to the customer/have we fixed identified bugs?
4. IMC updates the client on the process - if template or modules are ready to be handed over, encourage the client to work with them until next update.

## Sprint 5

Time for[Pre launch](https://processer.avidlyagency.com/imc/pre-launch)&#x20;